"The question in front of you is not who wins, but which path gives the town the most say in what this place becomes." Nick Larson of Red Rocks Gateway said that to Morrison's Board of Trustees on October 6, as reported by the Canyon Courier. That night the trustees voted 5–1 for his group. Since then, the shorthand around town has been "a grocery store and a hotel at the old speedway." The agreement itself is narrower and slower. It names a partner and lays out steps. Almost every one of those steps waits on something else first. The land has to reach the town, a plan has to be drawn, and residents have to be shown it in public.
The Vote Picked a Partner, Not a Plan
The parcel is about 16 acres along C-470, just north of the Morrison Road interchange. It was carved from the 125-acre property that used to be Bandimere Speedway. BusinessDen, writing in the Denver Post, reported that the board chose to partner with Red Rocks Gateway LLC. Its members are Larson, who runs Boulder-based Bear Peak Development; Jeremy Fey, mayor of Central City and son of famed Red Rocks concert promoter Barry Fey; Tyler Fey; Bryan Levitt; and Craig Campbell of Starwood Land. The Canyon Courier noted that state records show the LLC was formed on October 6, the same day the town approved the agreement.
The board approved a pre-development agreement. The draft in the October 6 board packet describes it as a framework for continued discussion and early work. It says outright that it grants no zoning, site plan or other development approvals. Those still go through town code and the usual decision-makers. No building is approved, and no grocer has signed on.
Two Offers on the Same 16 Acres
The trustees had a real choice. Bear Creek Development Corporation is a Morrison company that owns land right next to the parcel. It offered to buy the 16 acres outright. Here is how the two offers compared, based on the town packet and reporting from the Canyon Courier and BusinessDen:
| Bear Creek Development | Red Rocks Gateway | |
|---|---|---|
| Structure | Purchase of the land for $5.5 million | Partnership, with the town keeping ownership |
| Proposed uses | Retail, hotel, family entertainment, outdoor recreation, about 34 acres of open space, and housing | Grocery and lodging anchors, plus boutique, local and regional retail |
| Housing | Cut from an earlier 400 units to 50 | None; the agreement bars residential uses |
| Readiness | Built on a year of prior planning with the town | In early fact-finding on water and infrastructure |
Bear Creek owns 47 acres bordering the town's future parcel. About 20 acres of that is buildable, because part of it is hogback too steep to develop. Ross Bradley leads the company and is a fifth-generation Morrison property owner. He told the board his team was "about 365 days ahead of anybody else on this."
Housing ended up deciding it. Trustee Angela Bernhardt made the motion for Red Rocks Gateway. She told BusinessDen that Morrison is deeply skeptical of adding homes inside town limits. She described the goal this way: "We want it to be a draw to people who are going to Red Rocks, something that brings business in the winter." Trustee John Leonard cast the only no vote. "I think we should table both and have council go a little deeper on both proposals," he said, according to the Canyon Courier.
Why Nothing Starts Until Copart Finishes
The town doesn't own the 16 acres yet. Getting them involves a chain of steps, and they have to happen in order:
- 2023: Bandimere Speedway runs its final season. The NHRA Mile-High Nationals that July are its last national event in Morrison, as CPR reported.
- 2024: Copart, the car auction company, buys the property. Morrison votes on August 6 to annex it. Canyon Courier coverage of the annexation says that at the time, the rest of the site was described as outdoor vehicle storage and auction operations, with no live auctions, and with the grandstands, stadium lights and signs coming down.
- In exchange for annexation: Copart agrees to give the town the 16 acres closest to Morrison Road. A 2024 draft of the annexation agreement puts the price at $1, with the deed due after final plat approval.
- Now: According to the Canyon Courier, the land transfer won't happen until Copart's site development plan is approved, and that plan is still under review.
So a review of Copart's own project is what releases the gateway parcel. The Red Rocks Gateway agreement is written around that. Its deadlines are paused until Morrison takes title.
The Clock Written Into the Agreement
Once the town owns the land, the draft agreement sets these milestones:
- 270 days for due diligence.
- Nine months for the developer to get an expression of interest from a grocery or specialty grocery operator and from a hotel or other lodging operator. If documented, good-faith efforts come up empty, that doesn't count as a default as long as the search continues.
- Twelve months for a conceptual development plan. It must cover uses, building design, streets, trails, parking, water and sewer demand, phasing, renderings, and a pedestrian connection to Downtown Morrison.
- 360 days for a preliminary financing plan. After that, the town and developer decide whether an urban renewal authority is needed. The town keeps full legislative discretion on that question.
- November 1, 2027 is the agreement's initial end date. It moves back one day for every day before the town takes title.
The packet also asks for something beyond the anchors. The developer is to prioritize tenants that are "boutique, high-quality, destination-oriented, Colorado based, independent, and artisan." National and regional tenants are allowed as needed to support financing. Larson described the same balance to BusinessDen: "a mix of eclectic, independently-owned shops that hopefully will be patronized by citizens of Morrison, as well as more national brands, but not something that might be perceived as suburban sprawl."
Water Comes Before Any Tenant
Water and sewer capacity limit what can go on this land. Larson told BusinessDen that the group's early work centers on how to source water and build infrastructure. The draft agreement reserves 200 water taps and 200 equivalent residential units of sewer capacity for the project. Water service still needs a separate service agreement. Sewer taps wait on completion of the town's expanded wastewater plant. The developer also has to look into extra capacity from other providers.
For comparison, the 2024 draft annexation agreement caps Copart's auction center at three equivalent residential units of water, up to 1.11 acre-feet a year. Next door, the gateway parcel has 200 units set aside. Most of the old speedway will become a low-water storage yard. Nearly all the town's planned new water use is concentrated on the 16 acres by the Morrison Road exit, which is why Larson pitched that his deal "keeps the town water dedicated to this project."
Where Residents Come In
The draft requires at least two public presentations of the development plan. After them, the Board of Trustees gives written recommendations, and the developer has to consider and address them in the final plan. Because the plan is due within 12 months of the town taking title, those presentations are probably at least a year away. No date has been set.
The history explains why that requirement matters. The Canyon Courier reported on an earlier February community meeting about a previous conceptual master plan for the area, one that included housing. That meeting brought complaints from residents about notice and communication. This time, the agreement writes the public step in.
You don't have to wait for the presentations, though. The town's November calendar lists regular Board of Trustees meetings on Tuesday, November 3 and Tuesday, November 17, both at 6 p.m. Trustee community hours are Monday, November 16, at 6 p.m. at 110 Stone St. Community hours are the less formal setting, a good time to ask where Copart's site plan stands, since that review controls when everything else starts.
If you own near the Morrison Road interchange or along Bear Creek Avenue and want to talk through how a planned gateway project like this could factor into your plans, Trang Janick follows Morrison's agendas closely and is happy to walk through it with you. Start with a free home valuation and a conversation about where your property sits as this unfolds.